Intimation Of Temporary Shutdown Of Production Line At Unit II Of Pokarna Engineered Stone Limited (PESL) For New Equipment Installation And Integration From 5Th October 2024 To 7Th October 2024. |
10/04/24 18:00
We wish to inform you that our equipment supplier has requested additional time to complete the installation and integration of the new equipment. Consequently, the production line is now tentatively expected to resume by 7th October 2024, instead of the originally planned date of 5th October 2024.